PM Surya Ghar Application Process: Every Stage, Start to Finish

Rooftop solar installation on an Indian home with a bidirectional net meter, PM Surya Ghar application process 2026

Applying for the PM Surya Ghar subsidy takes five stages and, in most states, 60 to 90 days from registration to money in your bank account. The subsidy is ₹30,000 for a 1 kW system, ₹60,000 for 2 kW and ₹78,000 for 3 kW or larger, paid directly into your account after the system is commissioned. It never passes through the installer.

That last point is where most of the trouble starts. This guide covers what each stage actually involves, which documents you need before you begin, how to check where your application is stuck, and the three mistakes that cost people their subsidy entirely.

What the subsidy is worth in 2026

The Ministry of New and Renewable Energy fixes a benchmark cost and pays a percentage of it. The benchmark is ₹50,000 per kW for the first 2 kW, and central assistance is 60% of that. For the third kilowatt the rate drops to 40%, and above 3 kW nothing more is paid.

System size Benchmark cost Central subsidy
1 kW ₹50,000 ₹30,000
2 kW ₹1,00,000 ₹60,000
3 kW ₹1,45,000 ₹78,000
Above 3 kW Not capped ₹78,000, no more

A 5 kW system receives the same ₹78,000 as a 3 kW one. If subsidy is your main reason for going solar, 3 kW is the point where every further rupee comes out of your own pocket. Our 3 kW solar system price guide works through what that size actually costs.

Several states add their own money on top. Gujarat's is the most generous currently running, covering up to 90% of the benchmark for systems up to 2.18 kWp. The Gujarat 2 kW subsidy guide has the conditions, which are stricter than the headline suggests.

Four things to check before you apply

  1. The connection must be in your name. The subsidy is paid against an electricity consumer number, and the bank account must belong to the same person. Applications in a parent's name with a child's bank account are a common rejection.
  2. You need roof rights. Owned property is straightforward. In a flat or a rented house you need the owner's written consent, and in a housing society you need the society's resolution.
  3. Your sanctioned load matters. Most DISCOMs will not approve a system larger than your sanctioned load. Raising the load is a separate application and adds weeks.
  4. Decide on subsidy before you choose modules. Taking the subsidy means DCR modules, where both cell and module are made in India. That is a real constraint on price and availability, and it is explained further down.

The five stages, in order

Stage 1: Register on the national portal

Registration happens on the national rooftop solar portal. You select your state and DISCOM, enter your consumer number from a recent bill, and verify a mobile number. The login is an OTP sent to that number, so use one you will still have in three months.

Enter the consumer number exactly as the bill prints it, including any leading zeros. A mismatch here is the single most common reason an application never moves.

Stage 2: Technical feasibility approval

The DISCOM checks whether your local distribution transformer can take the extra capacity and whether your sanctioned load supports the system size. Published timelines range from 7 to 15 working days, though 15 to 30 days is more typical in practice.

If feasibility is refused, it is usually because the transformer is already carrying its permitted share of rooftop solar, or because the requested capacity exceeds your sanctioned load. Both are fixable, but not quickly.

Stage 3: Choose a vendor and install

The vendor must be registered on the portal for your DISCOM. You can pick any registered vendor, and you are not obliged to take the one the portal shows first or the one that calls you.

Installation at residential sizes takes two to three days. Get the module make, model and DC wattage written into the quotation, not just the system size, because the wattage is what the DISCOM inspects and what determines whether you stay under a state cap.

Stage 4: Net metering and commissioning

You apply for net metering, the DISCOM inspects the installation, and a bidirectional meter is fitted. This stage runs 7 to 30 days depending on the DISCOM, and it is where most applications sit the longest. Our net metering guide covers how exported units are credited afterwards.

The commissioning certificate issued at the end of this stage is the document that unlocks the subsidy. Nothing is paid before it exists.

Stage 5: Claim the subsidy

You upload the commissioning certificate and your bank details, including a cancelled cheque or passbook page. MNRE guidelines call for the subsidy to be processed within 15 days of DISCOM approval. Delays beyond that are common, but the money does arrive.

Payment is by Direct Benefit Transfer into your account. Be careful with any quotation presented as "subsidy already adjusted", because the installer cannot receive it on your behalf.

Documents you will need

  • Aadhaar, with the mobile number linked to it
  • A recent electricity bill showing the consumer number
  • Proof of property ownership, or a rental agreement with the owner's consent
  • Bank account details with a cancelled cheque or passbook page
  • A passport-size photograph

Upload fields vary slightly by DISCOM, so check the portal for your state before scanning everything.

How to check your application status

Log in to the portal with your registered mobile number and open the track application option. The status shows which of the five stages you are on. Three situations are worth acting on:

  • Feasibility pending beyond 30 days. Contact your DISCOM sub-division office with the application number. This rarely resolves itself.
  • Net meter pending after installation. Chase both the DISCOM and your vendor, since the inspection request is usually the vendor's job.
  • Subsidy pending more than 45 days after commissioning. Check that the bank details on the portal match the name on the electricity connection.

Where applications actually fail

Three mistakes account for most of the subsidies that never arrive.

  1. Non-DCR modules on a subsidised application. The subsidy requires cells and modules both made in India. Installing cheaper imported-cell modules disqualifies the application, and by then the system is on the roof.
  2. Commissioning before approval. Installing first and applying afterwards does not work. The feasibility approval has to exist before the system does.
  3. Name mismatches. Electricity connection, Aadhaar and bank account must all carry the same name. Correcting this mid-application means starting parts of it again.

If you give up the subsidy

There is a legitimate alternative. MNRE has clarified that residential consumers taking net metering under PM Surya Ghar who choose the give-it-up option are exempt from ALMM List-II, which covers solar cells, until 31 March 2027. In plain terms: forgo the subsidy and you may use modules built with imported cells.

That trade is worth running the numbers on. Non-DCR modules are usually cheaper per watt and available in higher wattages, so on a larger system the saving can approach the ₹78,000 you would have received. On a 2 or 3 kW system it almost never does. Either way, BIS registration still applies.

Conclusion

The process is not complicated, but it is unforgiving about sequence. Register first, get feasibility approval before anything is installed, keep the connection, Aadhaar and bank account in one name, and insist that the module make and DC wattage appear on the quotation. Do those four things and the ₹78,000 arrives on its own schedule.

The scheme runs to 31 March 2027. Applications started close to that date carry a risk nobody has published an answer to, because the portal says nothing about what happens to applications still open when the period ends.

Download the datasheets for our DCR and non-DCR ranges, or talk to us about module supply for a rooftop project. In Hindi, see सोलर पैनल लगाने का खर्च.

Frequently asked questions

How long does the PM Surya Ghar subsidy take?

Typically 60 to 90 days from registration to the money reaching your bank account. Feasibility approval takes 7 to 30 days, net metering and commissioning another 7 to 30, and the subsidy is meant to be processed within 15 days of DISCOM approval.

How much subsidy do I get for a 3 kW system?

₹78,000, which is the maximum under the scheme. A 1 kW system gets ₹30,000 and a 2 kW system ₹60,000. Anything above 3 kW still receives ₹78,000 and no more.

Does the subsidy go to me or to the installer?

To you, by Direct Benefit Transfer into the bank account registered on the portal. No part of it is paid to the installer, so treat any quotation described as having the subsidy already deducted with caution.

Can I use non-DCR panels and still get the subsidy?

No. Subsidised installations must use DCR modules, with both cell and module made in India. Consumers who formally give up the subsidy are exempt from ALMM List-II for cells until 31 March 2027, but they receive nothing. Our DCR explainer covers how to verify a module before it reaches the roof.

What documents are needed?

Aadhaar with a linked mobile number, a recent electricity bill, proof of property ownership or the owner's consent, bank details with a cancelled cheque, and a photograph. Exact upload fields vary by DISCOM.

Why is my application stuck at feasibility?

Usually because the local distribution transformer has reached its permitted share of rooftop solar, or the system exceeds your sanctioned load. If it has been pending over 30 days, take the application number to your DISCOM sub-division office.

What is the last date to apply?

The scheme period runs to 31 March 2027. No notice has been published about what happens to applications still in progress on that date, so leaving it until the final weeks carries real risk.